Morocco's CCAG-T and CCAG-EMO: what the general administrative clauses set out

SocoAfrica editorial team · Updated on

Construction workers laying steel reinforcement bars on a building site

The CCAG-T sets the performance conditions for public works contracts in Morocco, and the CCAG-EMO does the same for engineering studies and project management contracts. Here are their reference texts, their scope and the rules that weigh most on a company's cash flow.

Key points

  1. The CCAG-T was approved by Decree No. 2-14-394 of 13 May 2016, published in Bulletin officiel No. 6470 of 2 June 2016, and entered into force on 1 October 2016.
  2. Unless the special specifications provide otherwise, the performance bond is set at three percent of the initial contract value (Article 15 of the CCAG-T).
  3. The CCAG-EMO was approved by Decree No. 2-01-2332 of 4 June 2002, published in Bulletin officiel No. 5010 of 6 June 2002.
  4. Under Article 16 of Decree No. 2-22-431, general administrative clauses are approved by decree and apply according to the predominant category of services in the contract.

What a CCAG is in Moroccan public procurement

Decree No. 2-22-431 of 8 March 2023 on public procurement organises tender specifications on three levels: general administrative clauses (CCAG), common specifications (CPC) and special specifications (CPS). The CCAG set the administrative provisions applicable to all works, supply or service contracts, or to a category of them, and are approved by decree (Article 16).

When a contract covers several categories of services, the applicable CCAG is that of the predominant category. Where no CCAG exists for the services concerned, the contract is governed by the most suitable CCAG in force, which the contracting authority adjusts as needed in the CPS (Article 16).

The current CCAG were adopted under earlier decrees. Article 170 of the 2023 decree keeps texts adopted to implement the 2013 decree in force on a transitional basis until they are repealed or replaced. The CPS of each contract states which CCAG it refers to: that is the document to read first.

Morocco's CCAG-T: reference text and scope

The CCAG-T (sometimes written CCAGT) is the set of general administrative clauses applicable to works contracts. It was approved by Decree No. 2-14-394 of 6 Chaabane 1437 (13 May 2016), published in Bulletin officiel No. 6470 of 2 June 2016. Its Article 4 sets entry into force on 1 October 2016, and its Article 5 repeals Decree No. 2-99-1087 of 4 May 2000, which approved the previous works CCAG.

Under its first article, the CCAG-T sets the performance conditions for works contracts and defines the rights and obligations of the contracting authority and the contractor. Its 84 articles are organised in nine chapters: general provisions, contract guarantees, general obligations of the contractor, preparation and performance of the works, interruption of the works, prices and settlement of accounts, acceptance and guarantees, coercive measures, and settlement of disputes.

The CCAG-T also lists the documents that make up the contract. They include the acte d'engagement (signed bid form), the CPS, the schedule of prices and bill of quantities, the lump-sum breakdown and the detailed price breakdown when the CPS lists them as contractual documents, and the CCAG-T itself.

The guarantees set by the CCAG-T

Article 14 links financial guarantees to Dahir No. 1-56-211 of 11 December 1956: provisional and performance bonds and the retention money. The CPS sets their amount and may exempt the contractor from them in whole or in part.

Unless the CPS provides otherwise, the performance bond is set at three percent of the initial contract value, rounded up to the next dirham, and must be provided within twenty days of notification of the contract's approval (Article 15). Retention money is one tenth of each interim payment and stops growing once it reaches seven percent of the initial contract value plus any amendments (Article 64).

These guarantees may be replaced by joint and several personal guarantees from approved institutions (Article 17). The performance bond is returned and the retention money paid after release by the contracting authority, once the final acceptance report is signed (Article 19).

Acceptance and the guarantee period

Provisional acceptance takes place after the works have been checked for compliance. It transfers ownership and risk to the contracting authority and starts the guarantee period (Article 73 of the CCAG-T).

The guarantee period is twelve months from the provisional acceptance report, unless the CPS provides otherwise. During this period the contractor has an obligation of complete performance: it must remedy, at its own cost, the defects reported (Article 75).

The CCAG-EMO: engineering studies and project management

The CCAG-EMO is the set of general administrative clauses applicable to service contracts for engineering studies and project management (maîtrise d'œuvre) awarded on behalf of the State. It was approved by Decree No. 2-01-2332 of 22 Rabii I 1423 (4 June 2002), published in Bulletin officiel No. 5010 of 6 June 2002, and entered into force six months after publication (Article 2 of the decree).

It applies to engineering studies and project management contracts, and to contracts for technical inspection, testing and laboratory analysis in building and public works. The contracting authority may also refer to it for any other service contract. It does not apply to services entrusted to architects, which have their own regulations.

Its Article 12 refers to the texts in force for the provisional and performance bonds and leaves the CPS to set their amount. As with the CCAG-T, read the CPS to find out which version of the clauses applies and any derogations.

Preparing a public works project with the right partners

The CCAG-T rules on guarantees and subcontracting require reliable suppliers and subcontractors. SocoAfrica's Morocco business directory and its /verification/ page help you check a partner before including it in your bid.

If you are a buyer in the private sector, you can publish a private call for tenders free of charge on SocoAfrica's /rfq/ page. This service is separate from the public procurement portal and is not governed by the CCAG-T.

Frequently asked questions

Which text approves the CCAG-T in Morocco?
Decree No. 2-14-394 of 13 May 2016, published in Bulletin officiel No. 6470 of 2 June 2016, which entered into force on 1 October 2016.
What does CCAG-EMO stand for?
It is the set of general administrative clauses applicable to service contracts for engineering studies and project management, approved by Decree No. 2-01-2332 of 4 June 2002.
Does the CCAG-T still apply since the 2023 decree?
Article 170 of Decree No. 2-22-431 keeps texts adopted to implement the 2013 decree in force on a transitional basis until they are replaced. The CPS of each contract states which CCAG applies.
What is the guarantee period for a works contract?
Twelve months from the provisional acceptance report, unless the CPS provides otherwise (Article 75 of the CCAG-T).

This guide summarises official texts as of the date shown. Rules change: check them with the body cited before any transaction.